1. Designing the test environment set-up and identifying any required
infrastructure and tools are a
part of which phase
a)
Test Implementation and execution
b)
Test Analysis and Design
c)
Evaluating the Exit Criteria and reporting
d)
Test Closure Activities
2. Test Implementation and
execution has which of the following major tasks?
i.
Developing and prioritizing test cases, creating test data, writing test
procedures and
optionally
preparing the test harnesses and writing automated test scripts.
ii.
Creating the test suite from the test cases for efficient test execution.
iii.
Verifying that the test environment has been set up correctly.
iv.
Determining the exit criteria.
a)
i,ii,iii are true and iv is false
b)
i,,iv are true and ii is false
c)
i,ii are true and iii,iv are false
d)
ii,iii,iv are true and i is false
3. A Test Plan Outline contains
which of the following :-
i. Test Items
ii. Test Scripts
iii. Test Deliverables
iv. Responsibilities
a)
i,ii,iii are true and iv is false
b)
i,iii,iv are true and ii is false
c)
ii,iii are true and i and iv are false
d)
i,ii are false and iii , iv are true
4. One of the fields on a form
contains a text box which accepts numeric values in
the range of
18 to 25. Indentify the invalid Equivalance class
a)
17
b)
19
c)
24
d)
21
5. In a Examination a candidate
has to score minimum of 24 marks inorder to
clear the exam. The maximum that
he can score is 40 marks. Identify the Valid Equivalance values if the student
clears the exam.
a)
22,23,26
b)
21,39,40
c)
29,30,31
d)
0,15,22
6. Which of the following
statements regarding static testing is false:
a)
static testing requires the running of tests through the code
b)
static testing includes desk checking
c)
static testing includes techniques such as reviews and inspections
d)
static testing can give measurements such as cyclomatic complexity
7. Verification involves which of
the following :-
i.
Helps to check that we have built product right.
ii.
Helps to check that we have built the right product.
iii.
Helps in developing the product
iv.
Monitoring tool wastage and obsoleteness.
a)
Options i,ii,iii,iv are true.
b) i
is true and ii,iii,iv are false
c)
i,ii,iii are true and iv is false
d)
ii is true and i,iii,iv are false.
8. Component Testing is also
called as :-
i. Unit Testing
ii. Program Testing
iii. Module Testing
iv. System Component Testing .
a)
i,ii,iii are true and iv is false
b)
i,ii,iii,iv are false
c)
i,ii,iv are true and iii is false
d)
all of above is true
9. Link Testing is also called as
:
a)
Component Integration testing
b)
Component System Testing
c)
Component Sub System Testing
d)Maintenance
testing
10. What is the expected result
for each of the following test cases?
Rule 1 Rule 2 Rule 3 Rule 4
Conditions
Indian resident? False True True True
Age between 18 – 55? Don’t care False True True
Married? Don’t care Don’t care False True
Actions
Issue Memebership? False False True True
Offer 10% discount? False False True False
A.TC1:
Anand is a 32 year old married, residing in Kolkatta.
B.TC3:
Attapattu is a 65 year old married person, residing in Colombo.
a. A
– Issue membership, 10% discount, B – Issue membership, offer no discount. B
b. A
– Don’t Issue membership, B – Don’t offer discount. C
c. A
– Issue membership, no discount, B – Don’t Issue membership.
d.
Issue membership, no discount, B- Issue membership with 10% discount.
11. Methodologies adopted while
performing Maintenance Testing:-
a)
Breadth Test and Depth Test
b) Retesting
c)
Confirmation Testing
d)
Sanity Testing
12. Which of the following is
true about Formal Review or Inspection:-
i. Led by Trained Moderator (not the author).
ii. No Pre Meeting Preparations
iii. Formal Follow up process.
iv. Main Objective is to find defects
a)
ii is true and i,iii,iv are false
b)
i,iii,iv are true and ii is false
c)
i,iii,iv are false and ii is true
d)
iii is true and I,ii,iv are false
13. The Phases of formal review
process is mentioned below arrange them in the
correct order.
i. Planning
ii. Review Meeting
iii. Rework
iv. Individual Preparations
v. Kick Off
vi. Follow Up
a)
i,ii,iii,iv,v,vi
b)
vi,i,ii,iii,iv,v
c)
i,v,iv,ii,iii,vi
d)
i,ii,iii,v,iv,vi
14. Consider the following state
transition diagram of a two-speed hair dryer,
which is operated by pressing its
one button. The first press of the button turns it on to
Speed 1, second press to Speed 2
and the third press turns it off. Which of the
following series of state
transitions below will provide 0-switch coverage?
a.
A,C,B
b.
B,C,A
c.
A,B,C
d.
C,B,A
15. White Box Techniques are also
called as :-
a)
Structural Testing
b)
Design Based Testing
c)
Error Guessing Technique
d)
Experience Based Technique
16. What is an equivalence
partition (also known as an equivalence class)?
a) A
set of test cases for testing classes of objects
b)
An input or output range of values such that only one value in the range
becomes a
test
case
c)
An input or output range of values such that each value in the range becomes a
test
case
d)
An input or output range of values such that every tenth value in the range
becomes
a
test
case.
17. The Test Cases Derived from
use cases
a)
Are most useful in uncovering defects in the process flows during real world
use of
the
system
b)
Are most useful in uncovering defects in the process flows during the testing
use of
the
system
c)
Are most useful in covering the defects in the process flows during real world
use of
the
system
d)
Are most useful in covering the defects at the Integration Level
18. Exhaustive Testing is
a)
Is impractical but possible
b)
Is practically possible
c)
Is impractical and impossible
d)
Is always possible
19. Which of the following is not
a part of the Test Implementation and Execution
Phase
a)
Creating test suites from the test cases
b)
Executing test cases either manually or by using test execution tools
c)
Comparing actual results
d)
Designing the Tests
20. Which of the following
techniques is NOT a White box technique?
a)
Statement Testing and coverage
b)
Decision Testing and coverage
c)
Condition Coverage
d)
Boundary value analysis
21. A Project risk includes which
of the following :
a)
Organizational Factors
b)
Poor Software characteristics
c)
Error Prone software delivered.
d)
Software that does not perform its intended functions
22. In a risk-based approach the
risks identified may be used to :
i. Determine the test technique to be employed
ii. Determine the extent of testing to be carried out
iii. Prioritize testing in an attempt to find critical defects as
early as possible.
iv. Determine the cost of the project
a)
ii is True; i, iii, iv & v are False
b)
i,ii,iii are true and iv is false
c)
ii & iii are True; i, iv are False
d)
ii, iii & iv are True; i is false
23.
Which of the following is the task of a Tester?
i. Interaction with the Test Tool Vendor to identify best ways to
leverage test tool
on the project.
ii. Prepare and acquire Test Data
iii. Implement Tests on all test levels, execute and log the
tests.
iv. Create the Test Specifications
a)
i, ii, iii is true and iv is false
b)
ii,iii,iv is true and i is false
c) i
is true and ii,iii,iv are false
d)
iii and iv is correct and i and ii are incorrect
24. The Planning phase of a
formal review includes the following :-
a)
Explaining the objectives
b)
Selecting the personnel, allocating roles.
c)
Follow up
d)
Individual Meeting preparations
25. A Person who documents all
the issues, problems and open points that were
identified during a formal
review.
a)
Moderator.
b)
Scribe
c)
Author
d)
Manager
26. Who are the persons involved
in a Formal Review :-
i. Manager
ii. Moderator
iii. Scribe / Recorder
iv. Assistant Manager
a)
i,ii,iii,iv are true
b)
i,ii,iii are true and iv is false.
c)
ii,iii,iv are true and i is false.
d)
i,iv are true and ii, iii are false.
27. Which of the following is a
Key Characteristics of Walk Through
a)
Scenario , Dry Run , Peer Group
b)
Pre Meeting Preparations
c)
Formal Follow Up Process
d)
Includes Metrics
28. What can static analysis NOT
find?
a)
the use of a variable before it has been defined
b)
unreachable (“dead”) code
c)
memory leaks
d)
array bound violations
29. Incidents would not be raised
against:
a)
requirements
b)
documentation
c)
test cases
d)
improvements suggested by users
30. A Type of functional Testing,
which investigates the functions relating to
detection of threats, such as
virus from malicious outsiders.
a)
Security Testing
b)
Recovery Testing
c)
Performance Testing
d)
Functionality Testing
31. Which of the following is not
a major task of Exit criteria?
a)
Checking test logs against the exit criteria specified in test planning.
b)
Logging the outcome of test execution.
c)
Assessing if more tests are needed.
d)
Writing a test summary report for stakeholders.
32. Testing where in we subject
the target of the test , to varying workloads to
measure and evaluate the
performance behaviors and ability of the target and of
the test to continue to function
properly under these different workloads.
a)
Load Testing
b)
Integration Testing
c)
System Testing
d)
Usability Testing
33. Testing activity which is
performed to expose defects in the interfaces and in
the interaction between
integrated components is :-
a)
System Level Testing
b)
Integration Level Testing
c)
Unit Level Testing
d) Component
Testing
34. Static analysis is best
described as:
a)
The analysis of batch programs.
b)
The reviewing of test plans.
c)
The analysis of program code.
d)
The use of black box testing.
35. One of the fields on a form
contains a text box which accepts alpha numeric
values. Identify the Valid
Equivalence class
a)
BOOK
b)
Book
c)
Boo01k
d)
book
36. Reviewing the test Basis is a
part of which phase
a)
Test Analysis and Design
b)
Test Implementation and execution
c)
Test Closure Activities
d)
Evaluating exit criteria and reporting
37. Reporting Discrepancies as
incidents is a part of which phase :-
a)
Test Analysis and Design
b)
Test Implementation and execution
c)
Test Closure Activities
d)
Evaluating exit criteria and reporting
38. Which of the following items
would not come under Configuration
Management?
a)
operating systems
b)
test documentation
c)
live data
d)
user requirement document
39. Handover of Testware is a
part of which Phase
a)
Test Analysis and Design
b)
Test Planning and control
c)
Test Closure Activities
d)
Evaluating exit criteria and reporting
40. The Switch is switched off
once the temperature falls below 18 and then it is
turned on when the temperature is
more than 21. When the temperature is more
than 21. Identify the Equivalance
values which belong to the same class.
a)
12,16,22
b)
24,27,17
c)
22,23,24
d)
14,15,19
Answers:
1 b
11 a 21 a 31 b
2 a
12 b 22 b 32 a
3 b
13 c 23 b 33 b
4 a
14 c 24 b 34 c
5 c
15 a 25 b 35 c
6 a
16 b 26 b 36 a
7 b
17 a 27 a 37 b
8 a
18 a 28 c 38 c
9 a
19 d 29 d 39 c
10 c 20 d 30 a 40 c